Baden-Württemberg
A scoreboard cannot be funded through the sports federations. The 2026 equipment guidelines exclude score displays by name, and facility construction excludes spectator facilities.
- Programme
- Club facility construction and sports equipment funding of WLSB, Badischer Sportbund Nord and Badischer Sportbund Freiburg
- Grant
- 30 %
- Minimum
- EUR 3'500 total cost for building work, EUR 2'000 per item of equipment. The club needs more than 50 members.
- Scoreboard
- Excluded. The equipment guidelines list score displays and public address systems for spectators as not eligible.
- Application
- Many municipalities support clubs under their own guidelines. In Baden-Württemberg that, together with sponsors, is the realistic route.
Source: Sportgeräte-Förderrichtlinien 2026 (WLSB)
Bavaria
The BLSV pays up to 25 % since 2026. A scoreboard has little chance there, because the guidelines exclude spectator facilities and the equipment cost group.
- Programme
- Club facility construction under the Bavarian sports funding guidelines (SportFöR), handled by the BLSV
- Grant
- Up to 25 %, at most 40 % with supplements for joint projects
- Minimum
- EUR 10'000 eligible costs
- Scoreboard
- Not named. Spectator facilities and equipment are excluded, fixtures built into the structure count as the building. Confirm in writing with the BLSV first.
- Application
- Online via verein360, no fixed deadline. Start only after written approval to build; placing an order or buying material already counts as starting.
Source: BLSV, Info zum Kleinantrag (02/2026)
Berlin
The club investment programme only helps clubs with their own or long-term leased ground. Clubs playing on a district pitch ask the district sports office.
- Programme
- Club investment programme of the Senate (SFR VIP of 1 October 2022), plus programmes of the Berlin sports federation
- Grant
- 20 % grant and an interest-free loan of up to 40 %. The club's own share is at least 40 %.
- Minimum
- Grant of at least EUR 10'000
- Scoreboard
- Not named. According to its 2023 brochure, the Berlin sports federation funded digital measuring and scoring systems up to EUR 14'000 project cost. Ask there whether a scoreboard counts.
- Application
- Register projects under EUR 100'000 grant with the sport's association by 30 September of the previous year. Early start can be requested.
Source: Richtlinie SFR VIP (Senatsverwaltung)
Brandenburg
The new Golden Plan pays up to 80 %, but only from EUR 50'000 total cost. A scoreboard belongs in a larger building project there.
- Programme
- Golden Plan Brandenburg 2026 to 2029 (RL-GPB of 17 April 2026) and guideline A5 for facility construction of the state sports federation
- Grant
- Golden Plan up to 80 %. Guideline A5 80 %, half grant and half interest-free loan.
- Minimum
- Golden Plan above EUR 50'000 total cost. Guideline A5 above EUR 5'000, at most EUR 50'000 grant.
- Scoreboard
- Not named. The Golden Plan funds initial equipment within a building project; guideline A5 excludes spectator facilities.
- Application
- Golden Plan pre-application by 1 May for the following year with the district sports federation, guideline A5 by 1 July. Lottery funds of the education ministry are requested between 1 January and 30 September, at least three months before the project starts.
Source: Landessportbund Brandenburg, Goldener Plan
Bremen
SportInvest pays up to 50 %, but only for renovation and modernisation. Replacing an old scoreboard may fit, a first one hardly.
- Programme
- Municipal programme SportInvest (guideline of 3 March 2026) of the city of Bremen
- Grant
- Up to 50 %, at most EUR 125'000 per club
- Minimum
- Projects from EUR 1'000 to 250'000
- Scoreboard
- Not named. Stand-alone new builds are excluded; ask the sports office how a scoreboard is classed.
- Application
- In writing to the Bremen sports office by 31 October 2026. Federal or state programmes take priority. Bremerhaven has its own rules.
Source: Sportamt Bremen, SportInvest
Hamburg
The Hamburg sports federation funds club-owned facilities, renovation at 50 %. The guideline is only in the member portal.
- Programme
- Investment programme for club-owned facilities of the Hamburg sports federation, plus the IFB sports loan
- Grant
- 50 % for renovation, 15 % for new builds and extensions, as grant and loan
- Minimum
- IFB loan from EUR 20'000. Not public for the HSB programme.
- Scoreboard
- Not publicly regulated. Ask the HSB funding advice service.
- Application
- Through the HSB member portal. Apply for the IFB loan by 1 January or 1 July of the funding year.
Source: Hamburger Sportbund, Förderung
Hesse
Hesse does not exclude scoreboards anywhere. The state programmes by project size fit best; confirm with the ministry or the state sports federation first.
- Programme
- Three state programmes by project size (Weiterführung der Vereinsarbeit, Sportland Hessen, Vereinseigener Sportstättenbau) and the club fund of the state sports federation
- Grant
- State around 25 % for EUR 4'000 to 35'000 investment, around 30 % above, around 35 % from EUR 250'000. The sports federation pays up to 50 % for durable equipment, capped by the club's fund balance.
- Minimum
- EUR 4'000 investment for the state programmes
- Scoreboard
- Not named. The large programme funds the equipment of sports facilities but excludes spectator facilities.
- Application
- The two smaller state programmes at any time, online with the ministry. Placing an order counts as starting. From EUR 10'000 three comparable quotes are required.
Source: Hessisches Sportministerium, Förderprogramme
Mecklenburg-Western Pomerania
The sports infrastructure guideline pays up to 90 % of net cost if the municipality co-finances. Scoreboards are neither named nor excluded.
- Programme
- Sportinfrastrukturrichtlinie M-V of 14 August 2025, decided via the state sports federation, approved by the Landesförderinstitut
- Grant
- Up to 90 % of net cost if the municipality carries the national co-financing, otherwise up to 60 %
- Minimum
- Eligible cost above EUR 10'000, club with at least 31 members
- Scoreboard
- Not named. Equipment with sports apparatus is funded; ask the state sports federation how a scoreboard is classed.
- Application
- Information request via the district sports federation by 31 August for the following year, in the second round by 31 January. Work may start once receipt is confirmed, at your own risk.
Source: Landessportbund M-V, Baumassnahmen
Lower Saxony
The state sports federation pays up to 40 % but excludes spectator facilities and advertising structures. A scoreboard carrying sponsor ads has a hard time there.
- Programme
- Guideline for sports facility construction 2025 to 2027 of the LandesSportBund Niedersachsen
- Grant
- Up to 40 %, at most EUR 150'000
- Minimum
- Eligible cost from EUR 5'000
- Scoreboard
- Not named. Stands and spectator facilities are excluded, as are structures for perimeter and stand advertising.
- Application
- Through the LSB funding portal. Each district sports federation sets its deadline, usually between 31 August and 30 September for the following year. A consultation is mandatory from EUR 25'000, three quotes from EUR 3'000 order value. Work may start right after applying, at your own risk.
Source: Richtlinie Sportstättenbau 2025 bis 2027 (LSB Niedersachsen)
North Rhine-Westphalia
Moderne Sportstätte NRW is the strongest programme for a scoreboard. Equipment and digital modernisation are eligible, but the scoreboard alone rarely reaches the threshold.
- Programme
- Moderne Sportstätte Nordrhein-Westfalen (guideline of 1 July 2026), portal at the state sports federation, approved by NRW.BANK
- Grant
- Clubs that own the ground or hold a heritable building right 50 to 90 %, tenants and leaseholders 50 %
- Minimum
- Investment of at least EUR 50'000, grant of at least EUR 25'000. Several measures at the same ground may be bundled.
- Scoreboard
- Not named as such. The guideline and the call name equipment, digital modernisation and spectator facilities. Commercial use such as advertising is only allowed to a minor extent.
- Application
- Expression of interest in the LSB NRW portal; the city or district sports federation prioritises from the municipality's allocation. Request quotes only after the grant decision; before that, guide prices are enough.
Source: Landessportbund NRW, Moderne Sportstätte
Rhineland-Palatinate
The state's special programme pays up to 40 % for building projects of EUR 10'500 to 100'000. A scoreboard on a fixed foundation can fit as a building project.
- Programme
- Special state programme for club-owned sports facilities, via the Rheinland, Rheinhessen and Pfalz sports federations
- Grant
- Up to 40 %, so at most EUR 40'000
- Minimum
- Eligible cost from EUR 10'500 to 100'000
- Scoreboard
- Not named. Only structures fixed to the ground are eligible; a spectator shelter was funded in 2025. Equipment funding excludes time displays.
- Application
- By 30 September for the following year with the regional sports federation, with the municipality's consent. No order may have been placed yet.
Source: Landessportbund RLP, Sonderprogramm
Saarland
The sports planning commission decides case by case from sports lottery funds. Rates and thresholds are not published; funding often runs via the municipality.
- Programme
- Sports facility funding of the Sportplanungskommission (interior ministry and LSVS)
- Grant
- Not published; fixed amount or share within the budget
- Minimum
- Not published
- Scoreboard
- Not named; ask the commission's office.
- Application
- Informally to the LSVS or the ministry, at any time, with a statement from the municipality. Start only after the grant decision.
Source: Saarland, Sportplanungskommission
Saxony
The Saxon development bank pays up to 50 % and accepts projects under EUR 200'000 all year. The risk is being classed as a spectator facility.
- Programme
- Sports funding guideline (Sport-FRL), investment funding via the Sächsische Aufbaubank
- Grant
- Up to 50 %, own share at least 10 %
- Minimum
- Grant above EUR 2'500
- Scoreboard
- Not named. Technical installations and equipment are eligible, spectator facilities and stands are not.
- Application
- In the SAB portal, all year below EUR 200'000. Below EUR 100'000 of spending, work may start once the application is received, at your own risk.
Source: Sächsische Aufbaubank, Sportstättenförderung
Saxony-Anhalt
A case is on record here. In 2024 the state paid a football club half the cost of fencing and an LED scoreboard, more than EUR 43'200.
- Programme
- Guideline for municipal and club sports facility construction of 4 December 2024 via the Investitionsbank, plus Lotto-Toto Sachsen-Anhalt
- Grant
- State up to 50 %, lottery up to 50 % and at most EUR 75'000. Example from the state sports federation: state 50 %, lottery 35 %, club 15 %.
- Minimum
- EUR 10'000 total cost for the state, EUR 2'500 for the lottery
- Scoreboard
- Initial equipment is eligible where it is essential for operation. Spectator facilities are not excluded.
- Application
- Through the Investitionsbank portal by 31 August for the following year; the next date is 31 August 2027. Lottery at any time, at least four months before building starts.
Source: Landessportbund Sachsen-Anhalt, Landesförderung
Schleswig-Holstein
The state sports federation excludes scoreboards by name. That leaves the municipality, the LEADER region and sponsors.
- Programme
- Project funding guideline of the Landessportverband Schleswig-Holstein, in force since 1 January 2024
- Grant
- 20 %
- Minimum
- EUR 5'000 cost for building work, EUR 1'000 for equipment
- Scoreboard
- Excluded. The annex lists a scoreboard for spectators as not eligible.
- Application
- A LEADER region funded a sports club's scoreboard from its regional budget in 2025. Ask your region and your municipality.
Source: Richtlinie Projektförderung (LSV Schleswig-Holstein)
Thuringia
The state sports federation's guideline fits best by its wording: it funds permanently installed sports technology. A football club received EUR 4'000 in lottery funds for a digital scoreboard.
- Programme
- Guideline for club-owned sports facility construction of the Landessportbund Thüringen of 1 July 2024
- Grant
- Up to 60 %, at most EUR 500 per registered member
- Minimum
- EUR 6'000 total cost, own funds at least 10 %
- Scoreboard
- Permanently installed, durable sports equipment and technology is eligible. Mobile equipment is excluded.
- Application
- Register with the state sports federation by 1 August for the following year, with statements from municipality, district and district sports federation. The next date is 1 August 2027.
Source: Landessportbund Thüringen, Sportstättenbauförderung